The Problem

A tech startup occupying a 2,400-sqft office unit at The Earth, Bukit Jalil was undergoing a full interior renovation. The ID contractor needed all 5 aircond units removed before they could begin hacking walls, relocating electrical points, and installing new ceiling panels. The units — a mix of 3 Daikin wall-mounted and 2 Panasonic ceiling cassette models — were to be stored safely and reinstalled after the renovation.

The contractor had initially suggested their own workers remove the airconds, but the office manager wisely contacted Masters Aircond Service KL for professional aircond dismantling. Improper removal can damage compressors, leak refrigerant, and contaminate the system with moisture — leading to expensive repairs during reinstallation.

Our Assessment

We surveyed the office at The Earth, Bukit Jalil and documented all 5 units:

We scheduled the dismantling for the Saturday before renovation began, coordinating directly with the ID contractor to ensure the space was ready for hacking on Monday.

Work Timeline

Step 1: Refrigerant Pump-Down

Performed a proper pump-down procedure on all 5 systems — running each compressor while closing the liquid line valve to push refrigerant back into the outdoor unit. This preserves the gas charge and prevents environmental release.

Step 2: Electrical Disconnection

Isolated power supply to all units at the DB box. Disconnected signal and power cables from each indoor and outdoor unit. Labelled all wiring with unit numbers for easy reinstallation.

Step 3: Indoor Unit Removal

Carefully removed all 3 wall-mounted units and 2 ceiling cassettes. The cassettes required two technicians and a support frame to lower safely from the ceiling void without damaging the units.

Step 4: Outdoor Unit Removal

Disconnected and removed all 5 outdoor condensers from the ledge brackets. Capped all refrigerant line connections with brass caps to prevent moisture ingress during storage.

Step 5: Wrapping & Storage

Wrapped all indoor and outdoor units in protective plastic and bubble wrap. Stored them in the building's designated storage area on Level B1, as arranged with building management.

Results

All 5 units safely removed and stored
Zero refrigerant loss during pump-down
All piping preserved for reuse
Labelled wiring for easy reinstallation
Total cost: RM750 (RM150/unit)
Completed in half a day (8am–1pm)

Lessons & Advice

Never let general contractors or renovation workers remove your aircond units. We've seen too many cases where units were yanked off walls without pumping down the refrigerant — resulting in complete gas loss (RM150–300 to recharge per unit) and moisture contamination that damages the compressor over time.

Professional dismantling costs RM120–180 per unit at Masters Aircond Service KL, depending on the unit type and accessibility. It's a small investment that protects equipment worth thousands of ringgit. We also recommend a full chemical wash or chemical overhaul before reinstallation — it's the perfect time to deep-clean since the units are already dismounted.

If you're planning a renovation, contact us early. We coordinate with your contractor to ensure the dismantling and later reinstallation fit neatly into the renovation timeline with zero delays.

Kevin Chong

Kevin Chong

Founder & Senior Technician

Kevin founded Masters Aircond Service KL with one goal: honest, reliable aircond servicing across Kuala Lumpur. With over 12 years in the industry, he personally oversees every major project.

Renovating? Let Us Handle the Aircond

Masters Aircond Service KL provides professional aircond dismantling and reinstallation across Bukit Jalil and KL. Safe removal, proper storage, hassle-free.

WhatsApp Us Now